New Deal era South Catamount Dam receiving facelift from Springs Utilities

Beneath an enclosure attached to the steeply sloping wall of the South Catamount Dam on Thursday, crews painstakingly blasted away years of wear, vacuumed up the debris and applied a fresh layer of a specialized epoxy.

When they’re done, they will move the enclosure and repeat the process until they’ve covered the 145,000-square-foot steel facing of the dam with the battleship-gray coating. Colorado Springs Utilities hopes to have the coating process completed by the end of October.

“The dam itself is in remarkable condition,” Chief Dam Safety Engineer Bill Sturtevant said of the 87-year-old structure. “The steel is in great shape. It’s still relatively close to full dimension, which means it’s as thick as it was the day it was put in.”

During the blasting process, the steel is taken down to bare metal and slightly textured so that the protective coating can better adhere, Sturtevant said.

Weather can make the process tedious. Not only can rain and wind hinder the work, but so can heat and cold. In the bright Colorado sun, the steel can heat considerably, even on a mild day.

Crews are also busy digging up several massive 1937-vintage valves and 1.5 miles of piping, all of which will be either replaced or, in a few cases, removed, according to Project Manager Larysa Voronova. The water intake structure, now exposed for the first time since Franklin D. Roosevelt occupied the White House, will be removed and the two pipes it houses will be replaced by a single, larger pipe and a more efficient control structure.

That pipe runs beneath the dam, where a new valve house is being built. Also being replaced is much of the original concrete. The refurbishment is expected to last for 50-75 years.

“When we do a project of this magnitude, the idea is to get everything done while the reservoir is down so we don’t have to do it again,” Sturtevant said.

Once the work is completed, it will take time to refill the reservoir.

“There is a safety procedure associated with filling the reservoir,” Voronova said. “We’re going to start filling the reservoir at the end of 2025 and are hoping to at least have it half full by the summer of 2026.”

In the meantime, CSU officials are pleading with hikers, biker, campers and fishermen to observe the closures and stay away.

Aside from the reservoir proper, some area trails are also closed for public safety. Crystal Creek Reservoir and North Catamount Reservoir, also located in the North Slope Recreation Area, remain open but access to North Catamount is hike-in only from Teller County. Visit csu.org/southcatamount for more information and a map of trail closures.

It’s a huge project. During a tour given by CSU to media members on Thursday, large vehicles were navigating the narrow roads and excavators were digging up pipes and valves. It’s not a friendly site for recreation.

Workers relayed an anecdote about two hikers who went past “do not enter” signs only to get offended when they were nearly hit with the shovel of an excavator. They were asked to leave but instead continued their hike.

“It’s a very dangerous situation with the number of contractors and the type of construction we’re doing,” Sturtevant said. “There’s very large equipment moving around, there’s a lot of activity.”

South Catamount is one of only five steel-faced dams in the United States. Four of those are among the 25 reservoirs under CSU’s purview.

These steel-faced dams were constructed in the 1930s as part of Roosevelt’s Works Progress Administration program — a post-Depression era program that put people back to work on large-scale public works projects.

A worker rappels down the upstream face of the South Catamount Reservoir dam July 11 while working on the recoating of the dam’s steel face that was constructed in 1937. Crews are grit-blasting the steel surface of the dam, then recoating it. The project, which was started in the fall of 2023, also includes the replacement of the dam’s infrastructure and the underground pipe that transports the water to other reservoirs in the Colorado Springs Utilities water system. The project is scheduled to be finished by the summer of 2026. (Christian Murdock, pikes peak courier)
A worker rappels down the upstream face of the South Catamount Reservoir dam July 11 while working on the recoating of the dam’s steel face that was constructed in 1937. Crews are grit-blasting the steel surface of the dam, then recoating it. The project, which was started in the fall of 2023, also includes the replacement of the dam’s infrastructure and the underground pipe that transports the water to other reservoirs in the Colorado Springs Utilities water system. The project is scheduled to be finished by the summer of 2026. (Christian Murdock, pikes peak courier)
Workers replace a valve this month as part of the Colorado Springs Utilities’ South Catamount Reservoir dam rehabilitation project. The pipe from South Catamount to the Crystal Creek Reservoir will be replaced. (Christian Murdock, The Gazette)
Workers replace a valve this month as part of the Colorado Springs Utilities’ South Catamount Reservoir dam rehabilitation project. The pipe from South Catamount to the Crystal Creek Reservoir will be replaced. (Christian Murdock, The Gazette)
LEFT: Project manager Larysa Voronova walks below the upstream face of the South Catamount Reservoir dam July 11 while touring the project. The dam, which opened in 1937, was last rehabilitated in the 1970s. RIGHT: Workers replace a valve July 11 as part of the Colorado Springs Utilities South Catamount Reservoir dam rehabilitation project. All of the pipe from South Catamount to the Crystal Creek Reservoir will be replaced. (photos by Christian Murdock, Pikes Peak COurier)
LEFT: Project manager Larysa Voronova walks below the upstream face of the South Catamount Reservoir dam July 11 while touring the project. The dam, which opened in 1937, was last rehabilitated in the 1970s. RIGHT: Workers replace a valve July 11 as part of the Colorado Springs Utilities South Catamount Reservoir dam rehabilitation project. All of the pipe from South Catamount to the Crystal Creek Reservoir will be replaced. (photos by Christian Murdock, Pikes Peak COurier)
Crews work on the South Catamount Reservoir dam that was finished in 1937 as part of President Franklin Roosevelt’s Work Progress Administration — a post-Depression area program to put people back to work on large-scale public works project. (photos courtesy of Jennifer Jordan, colorado springs utilities)
Crews work on the South Catamount Reservoir dam that was finished in 1937 as part of President Franklin Roosevelt’s Work Progress Administration — a post-Depression area program to put people back to work on large-scale public works project. (photos courtesy of Jennifer Jordan, colorado springs utilities)
Old water pipes from 1937 lie next to the road as crew work to replace the pipes between the South Catamount Reservoir and Crystal Creek Reservoir Thursday, July 12, 2024. (The Gazette, Christian Murdock) (Christian Murdock, The Gazette)
Old water pipes from 1937 lie next to the road as crew work to replace the pipes between the South Catamount Reservoir and Crystal Creek Reservoir Thursday, July 12, 2024. (The Gazette, Christian Murdock) (Christian Murdock, The Gazette)
A worker cleans the surface of the upstream face of the South Catamount Reservoir dam Thursday, July 11, 2024, while working on the recoating of the dam’s steel face that was constructed in 1937. Crews are grit-blasting the steel surface of the dam, then recoating it. The project, which was started in the fall of 2023, also includes the replacement of the dam’s infrastructure and the underground pipe that transports the water to other reservoirs in the Colorado Springs Utilities water system. The project is scheduled to be finished by the summer of 2026. (The Gazette, Christian Murdock) (Christian Murdock, The Gazette)
A worker cleans the surface of the upstream face of the South Catamount Reservoir dam Thursday, July 11, 2024, while working on the recoating of the dam’s steel face that was constructed in 1937. Crews are grit-blasting the steel surface of the dam, then recoating it. The project, which was started in the fall of 2023, also includes the replacement of the dam’s infrastructure and the underground pipe that transports the water to other reservoirs in the Colorado Springs Utilities water system. The project is scheduled to be finished by the summer of 2026. (The Gazette, Christian Murdock) (Christian Murdock, The Gazette)
A family of Canada geese swim across the lowered South Catamount Reservoir Thursday, July 11, 2024. (The Gazette, Christian Murdock) (Christian Murdock, The Gazette)
A family of Canada geese swim across the lowered South Catamount Reservoir Thursday, July 11, 2024. (The Gazette, Christian Murdock) (Christian Murdock, The Gazette)
The water behind the South Catamount dam, as seen July 11 was lowered to allow for the rehabilitation of the 1937 dam. The reservoir will be filled and reopened to the public for the 2026 summer season. (Christian Murdock, Pikes Peak COurier)
The water behind the South Catamount dam, as seen July 11 was lowered to allow for the rehabilitation of the 1937 dam. The reservoir will be filled and reopened to the public for the 2026 summer season. (Christian Murdock, Pikes Peak COurier)
A worker cleans up after grit-blasting the steel on the upstream face of the South Catamount Reservoir dam July 11 while recoating it. The project, which was started in the fall of 2023, also includes the replacement of the dam’s infrastructure and the underground pipe that transports the water to other reservoirs in the Colorado Springs Utilities water system. (Christian Murdock)
A worker cleans up after grit-blasting the steel on the upstream face of the South Catamount Reservoir dam July 11 while recoating it. The project, which was started in the fall of 2023, also includes the replacement of the dam’s infrastructure and the underground pipe that transports the water to other reservoirs in the Colorado Springs Utilities water system. (Christian Murdock)