Pueblo officials want enforcement assurances if SDS deal with Colorado Springs is to be reached
PUEBLO – Pueblo County commissioners were gracious but appeared unappeased Monday by Colorado Springs leaders’ promises to resolve stormwater issues that have hit downstream communities hard.
And the Pueblo City Council, in a symbolic gesture, unanimously passed a resolution Monday night to support county efforts to hold Colorado Springs accountable for stormwater problems along Fountain Creek and recommend a 10-year plan in exchange for allowing Colorado Springs Utilities to keep its 1041 permit and commence with the Southern Delivery System.
Colorado Springs leaders since last year have accepted responsibility for the long-running stormwater problems, and they have proposed a 10-year intergovernmental agreement with provisions for enforcement.
Mayor John Suthers and the Colorado Springs City Council have vowed to spend more than $19 million a year fixing stormwater problems, and Pueblo County and Colorado Springs consulting engineers have collaborated to identify and prioritize those needs. At least 80 percent of projects this year will directly benefit Pueblo County, said Travis Easton, public works director for Colorado Springs, during a presentation to the county commissioners.
Work on the first priority project, a detention pond on Sand Creek, starts next week. Colorado Springs has hired Richard Mulledy, a professional engineer who previously worked for the City of Pueblo and most recently has been deputy director of water resources for Matrix Design Group in Colorado Springs, as Stormwater Division manager. He starts work Feb. 22.
While Colorado Springs leaders outlined a long list of measures being undertaken to address the stormwater issue, officials with Colorado Springs Utilities and the city remained baffled by the intertwining of what they see as two separate measures.
Utilities has met every condition of its 1041 project, said SDS Director John Fredell. On April 27, the project is to start pumping 5 million gallons of Arkansas River water a day initially from Pueblo Reservoir to Pueblo West, Colorado Springs, Security and Fountain.
Colorado Springs, meanwhile, is negotiating with the U.S. Environmental Protection Agency, which accused the city in October of neglecting stormwater needs for years. A two-day EPA inspection turned up deteriorating infrastructure, inadequate inspections and excessive sedimentation, among other problems.
At stake is the city’s own water permit.
The effort to hold Utilities’ 1041 permit ransom because of municipal stormwater failures by Colorado Springs is mixing apples and oranges, Suthers and Fredell noted. But Pueblo city and county leaders see the permit for the $825 million SDS as the best bargaining chip to get what they want.
When Suthers assured Pueblo city leaders that more than $250 million worth of stormwater work would be done in 10 years, newly elected Pueblo City Councilwoman Lori Winner cited a CH2M Hill engineering study from 2013 saying the stormwater needs amounted to more than $500 million.
“It’s really a wish list,” Suthers said. “The voters are not going to give me $50 million a year. I don’t want to make any agreement contingent on whether (local anti-tax activist) Doug Bruce likes it or not.”
Because Colorado Springs voters repeatedly voted down stormwater measures in recent years, as Bruce exhorted them to oppose the “rain tax” in 2014, Suthers and the council decided to pay for that need directly from the city budget. The fire and police departments were squeezed and raises frozen in the 2016 budget to find the money.
“I’ll never come up with $500 million,” Suthers said in a rare show of exasperation. “There’s just no way in hell.”
The Pueblo commissioners repeatedly intoned the need for solid enforcement measures in any intergovernmental agreement.
“We as a community have heard a lot of promises from your community for a very long time,” Commissioner Terry A. Hart said. ” . Whatever we do going forward, we can’t base it on mere promises.”
The only “silver lining” in the city’s problems with the EPA is that any resulting federal decree will serve as a mandate, ensuring that the pact with Pueblo County is enforced, Suthers said.
Another enforceable provision would be to designate Utilities, as a long-time city enterprise, to meet the financial requirements through its annual “excess revenue” returns to the city if Colorado Springs failed to meet its stormwater obligation.
Hart questioned whether a fifth branch of Utilities couldn’t be created to handle stormwater. But that would require a change in the City Charter, approval by Colorado Springs voters, who have opposed all recent stormwater measures, and other complex machinations involving ratepayers who don’t live in the city, said Andres Pico, chairman of the Utilities board.
Commissioner Sal Pace questioned whether the SDS couldn’t be turned off if sufficient stormwater work isn’t done, or whether the project could be delayed while a new agreement is drafted.
Neither idea is feasible, however. The SDS is a sprawling system with water treatment plants, pumping stations and precise chemical requirements that cannot be stopped once it gets started. And the notion of delaying it would cause Utilities to lose time on its warranties, some on millions of dollars worth of work and equipment, Suthers said.
Asked what would happen after a 10-year agreement, the mayor said language could be added to renegotiate the pact every 10 years, with a clause for inflationary increases.
“We’re going to continue our negotiations with the county and everybody else involved and try to resolve this issue,” Suthers said Monday evening.
As for the commissioners’ questions earlier in the day, he said, “I thought they brought up good points that can be the basis for more negotiations.”