Stormwater meeting could help ease tensions between Colorado Springs, Pueblo
Sediment in Fountain Creek has increased 278-fold since the Waldo Canyon fire, pushing stormwater levels far higher, Pueblo County commissioners learned Friday.
And while sediment grew from 90 to 25,075 tons per year, water yields increased from 2,500 to 4,822 acre-feet a year, says a new report by Wright Water Engineers Inc. of Denver.
While commissioners were hearing the report, Pueblo City Council members were expressing concern about sediment to Colorado Springs councilors during a meeting on stormwater.
“It’s not hard to flood (Fountain Creek) because of that sediment buildup. That’s one of the difficulties we’re facing,” said Pueblo Council President Steve Nawrocki. “The water doesn’t have to be that high anymore to start flooding because of the sediment buildup.”
Colorado Springs Mayor John Suthers and the City Council have vowed to commit $19 million a year to stormwater remediation efforts, beginning in January.
But some Pueblo leaders remain skeptical, as previous administrations made similar promises that came to naught.
“I was on the City Council when we signed the SDS (Southern Delivery System) permit,” Pueblo Councilman Bob Schilling said. “I don’t think we were really treated truthfully. I’m from Missouri, the ‘Show Me’ state. But now I have high hopes.”
Colorado Springs Council President Merv Bennett acknowledged those concerns.
“We proved over the past four years: When the mayor and council move in two different directions, nothing gets done,” Bennett said. “I want this (unified effort) to become our standard operating procedure. It’s easy for us to talk. You do need to evaluate us by our actions, and that’s OK.”
Pueblo residents face another imminent threat, too, said City Manager Sam Azad.
“What we really worry about – because of all the water, sediment increases and higher flow level – if we can’t get re-certified from the Army Corps of Engineers for a 100-year flood zone, it will affect flood insurance,” Azad said.
“For immediate attention, we need to take care of that sediment that’s coming downstream. I don’t know how much $19 million will mitigate in the future, but I think it’s the right step and right time to move forward.”
The SDS, a mammoth $829 million water project being completed by Colorado Springs Utilities, required a prized 1041 permit with many restrictions.
“That’s really our ace in the hole,” Schilling said.
Once the SDS starts pumping water in April – up to 50 million gallons a day to Colorado Springs, Pueblo West, Security and Fountain – CSU will deliver $10 million a year for five years to the Fountain Creek Watershed, Flood Control and Greenway District, Bennett noted.
But, said Azad, “Our needs are above and beyond whatever’s stated in that 1041. We are dealing with some immediate issues in Fountain Creek right now … . If we can get assurances that at least some of that will be mitigated, that would be great.”
Back in Pueblo, the commissioners learned that the watershed gets more input than output, with huge quantities of sediment pouring in and accumulating until a large storm pushes it downstream.
High stream flows in the creek and two of its tributaries, Monument and Sand creeks, could send gravel-size particles downstream, the Wright report says.
The 930-square-mile Fountain Creek watershed has changed continually since 1980 because of imported water, urbanization and reduced capacity at Pueblo levees, the report says.
So the creek gets more flow and sediment, higher rainfall-runoff response, severe erosion and widespread channel instability, the engineers reported. More sediment is carried into the creek at Fountain now than is carried out at Pueblo, they report. The entire watershed must be addressed, and the solution likely will take decades, officials agree.
Detention ponds at Waldo Canyon, $4 million in repairs at Clear Spring Ranch and requirements for multiple detention ponds on new developments all have helped, Colorado Springs leaders said.
But the enormity of the problem isn’t lost on them.
Once the City Council and Pueblo County approve an intergovermental agreement being designed now, Colorado Springs officials will “look at critical issues that have the greatest impact and commonality,” Bennett said, and begin spending $19 million a year to address them.