CDOT says it has ‘cobbled together’ money for Cimarron/I-25 interchange
The Colorado Department of Transportation has pulled funds “from a variety of sources” to ensure that the Pikes Peak region’s most important road project will get the money it needs.
Local officials were concerned this month when they learned that all of the funds to complete the $95 million I-25/Cimarron Interchange project had not been found amid the Transportation Department’s mix of money.
Since then, after some scrambling, the department believes it has the necessary money.
“I-25 and Cimarron at our commission meeting next month will be fully funded,” said Les Gruen, the state transportation commissioner who represents El Paso County.
“There was never any doubt about that,” he said at a monthly meeting of the Pikes Peak Area Council of Governments on Wednesday.
“There was some doubt as to where we were going to find (the funds). We’re going to be in good shape about that.”
The massive project was approved as part of the state’s Responsible Acceleration of Maintenance and Partnerships Program in October.
That program allows CDOT to advance $300 million a year for five years to pay for projects, or $1.5 billion for projects statewide.
Some of the money for the Cimarron Street interchange came from projects at Fort Carson’s Gates 5 and 6 off Colorado 115, said Bob Wilson, CDOT spokesman.
Those projects cost less than expected, and the savings were directed to the I-25/Cimarron Interchange project, he said.
Money also came from safety funds and future bridge repair funds, he said.
The interchange, Wilson said, “is considered a safety project as well.”
In all, the Transportation Department managed to come up with $53 million.
“We were able to cobble together a pretty good deal, but this is an important project,” Wilson said.
Construction, he said, is on target to start in 2015.
Part of the issue arose because the transportation department decided to move from a “decentralized to a centralized program,” for project funding, “especially on projects of this magnitude,” Gruen said.
For local officials, the news brought a sense of relief.
The I-25/Cimarron interchange is critical for Colorado Springs, El Paso County and western communities in Teller County, including Woodland Park and Cripple Creek, where limited stakes gaming is allowed.
“Good news, by the way, from the CDOT folks,” said Dennis Hisey, El Paso County commissioner and chairman of the PPACG board.
As far back as 1929, members of the Sheet Metal Workers Local Union #9 have been making floats for the St. Patrick’s Day parade in Colorado Springs. Students from the Colorado Sheet Metal Training Institute, associated with the union, now help build the float every year. Students Scott Boleraczky and Kim Davis (right to left) attach robot leprechauns to the top of a metal pot on Tuesday, March 11, 2014. (The Gazette/Jerilee Bennett)