Intersection at Powers, Woodmen finsihed ahead of schedule

A massive project to build an interchange at the intersection of Powers Boulevard and Woodmen Road, two of the region’s busiest roads, has been completed within budget and ahead of schedule, the Colorado Department of Transportation said Thursday.

The $26 million project, begun in January 2007, was expected to be finished in spring or summer of 2009. But an “amazing effort” by contractor R.E. Monks saw it done months ahead of schedule, said CDOT resident engineer Mark Andrew. He said the contractor’s willingness to work at night, nice weather this fall and a good plan for phasing work played a large role in getting the project done early.

The new interchange carries six lanes of Powers Boulevard over Woodmen Road, on two parallel bridges unimpeded by traffic lights. Woodmen changes from a six-lane road west of the interchange to four lanes under the bridge, so it matches an ongoing county project that is making Woodmen four lanes all the way to Falcon. Andrew said CDOT left room to expand Woodmen east to six lanes should the county need to do so.

Ted Tjerandsen, consultant project manager working for CDOT, provided a few figures to highlight the scope of the project:— 500,000 yards of dirt was moved for the interchange, 200,000 of that total in just 10 days with crews working 22 hours a day.— 65,000 tons of hot-mix asphalt was laid down.— 1,700 cubic yards of concrete was used to build the two divided bridges, each spanning 220 feet, over Woodmen.— 330,000 pounds of reinforcing steel was embedded in the interchange.— At the peak of construction during the summer, 40 to 60 workers a day labored on the project.— $1.5 million to $2 million was spent on drainage work.— $3.5 million was spent to relocate utilities so roadways could be constructed.

Both men said the project was challenging, in part, because crews had to work around busy traffic – and that traffic had to be routed to minimize delays for drivers. An average of 100,000 vehicles travel through the interchange area each day – 60,000 on Powers, and 40,000 on Woodmen.

The only major glitch occurred when a pouring machine broke and laid down too much concrete on the interchange bridge deck. That concrete had to be removed and the bridge re-engineered.

The project also was hit by this summer’s nationwide shortage of polymer-enhanced asphalt, which is used to extend the life of a road. Andrew said the project had to use regular asphalt, but he said it was a “good mix” that ought to weather well.

There were no major injuries or fatalities on the job.

As part of the project, CDOT also completed the first section of a multiuse trail that will carry bicyclists and pedestrians through the interchange area. The trail eventually will be part of a trail system planned by the city of Colorado Springs and El Paso County that will parallel Woodmen Road from Interstate 25 to Falcon.

The state paid for a portion of the project, but the majority of funding came from the federal government.

nternationally known sculptor Patrick Dougherty worked on a site-specfic sculpture with elm and cottonwood saplings and twigs Tuesday at the corner of Cache La Poudre St. and Cascade Ave. Photo by Carol Lawrence, The Gazette

CAROL LAWRENCE,THE GAZETTE